Find building materials at lowest prices in 10 mins
Find the lowest prices in10 minutesHyderabad
Clyft
Concrete cube compressive strength test

Concrete Cube Test: How Many Samples and What Results Mean

Clyft Editorial Team3 min read

Mix proportions, water, compaction and curing all decide concrete strength, and none can be seen once the slab is cast. Cubes are the record of what actually went in.

How Cubes Are Made

  1. Take concrete from the pour as it is being placed — not a special batch.
  2. Fill 150 mm steel moulds in layers, compacting each by rod or vibration.
  3. Mark each cube with the date, member and grade.
  4. Leave in the moulds, covered, for about 24 hours.
  5. Demould and cure in clean water until testing.
  6. Test at 7 and 28 days in a compression testing machine; strength = failure load ÷ area.

How Many Samples?

IS 456 sampling frequency:

Quantity of concrete in the workNumber of samples
1 – 5 m³1
6 – 15 m³2
16 – 30 m³3
31 – 50 m³4
51 m³ and above4 + 1 per additional 50 m³

A sample is normally three cubes for each test age. A typical 12 m³ house slab therefore needs two samples — six cubes for 28 days, plus cubes for 7 days.

Reading 7-Day Results

Cement7-day strength as share of 28-day (typical)
OPCAbout 65 – 70%
PPCLower; gains more between 7 and 28 days

So M20 OPC concrete showing roughly 13–14 N/mm² at 7 days is on track. The 28-day result is what counts; IS 456 sets acceptance criteria for groups of results and individual results.

If Results Are Low

  1. Check the test — cube making, curing and testing can themselves be faulty.
  2. Non-destructive tests on the structure — rebound hammer, ultrasonic pulse velocity — to map strength.
  3. Core tests — cylinders cut from the member and crushed.
  4. Engineer's decision — accept, strengthen, or replace.

The Short Version

Cast cubes from every important pour, at the frequency IS 456 sets, cure them properly and test at 7 and 28 days. They cost little and are the only proof of what is inside your slab.

Frequently Asked Questions

What is the concrete cube test?

Fresh concrete from a pour is cast into 150 mm cube moulds, cured in water, and crushed in a compression testing machine at 7 and 28 days to measure compressive strength. It checks that the concrete actually placed reached its grade.

How many cubes should be taken?

IS 456 sets sampling by quantity: one sample for 1 to 5 cubic metres, two for 6 to 15, three for 16 to 30, four for 31 to 50, and four plus one per additional 50 cubic metres. Each sample is usually three cubes per test age.

What strength should M20 cubes reach at 7 days?

OPC concrete commonly reaches roughly two-thirds of its 28-day strength at 7 days. PPC concrete gains strength more slowly, so its 7-day result is lower relative to 28 days.

What if cubes fail the test?

The engineer may order further tests on the structure — core cutting, rebound hammer or ultrasonic tests — and decide whether the member is acceptable, needs strengthening, or must be replaced.

Which standard covers the cube test?

IS 516 covers methods of tests for strength of concrete; IS 456 sets sampling frequency and acceptance criteria.

Get the lowest price in Hyderabad

Cement, TMT steel and AAC blocks are three-quarters of a house's material bill. See today's Hyderabad prices before you ask for quotes.

More Guides

Get the Clyft app

Compare quotes from suppliers and order in minutes.

Download on the App StoreGet it on Google Play
The Clyft app showing supplier quotes for a cement order