Calculating cement and sand for plastering

Plaster Quantity Calculation: Cement and Sand per 100 Sq Ft

Clyft Editorial Team3 min read

Plaster covers every wall and ceiling twice over — inside and out — so it adds up to a surprising share of a house's cement. A quick, consistent method lets you estimate it from the drawings.

The Method

  1. Area: wall or ceiling area to be plastered, in m² (deduct large openings).
  2. Wet volume: area × thickness (in metres).
  3. Dry volume: wet volume × 1.27.
  4. Allowance: + 20% for joints, hollows and unevenness.
  5. Split by ratio: cement = dry volume × (1 ÷ sum of parts); sand = dry volume × (sand parts ÷ sum).
  6. Cement in bags: m³ × 1,440 kg ÷ 50.

Worked Examples (per 100 sq ft = 9.29 m²)

PlasterThicknessMixWet vol.Dry + 20%CementSand
Internal wall12 mm1:60.111 m³0.170 m³35 kg ≈ 0.7 bag0.146 m³ ≈ 5.2 cft
External wall20 mm1:40.186 m³0.283 m³82 kg ≈ 1.6 bags0.226 m³ ≈ 8.0 cft
Ceiling6 mm1:30.056 m³0.085 m³31 kg ≈ 0.6 bag0.064 m³ ≈ 2.3 cft

A Whole-Room Example

A 12 × 12 ft room with 10 ft walls, one door (3 × 7 ft) and one window (4 × 4 ft):

  • Wall area: 4 × 12 × 10 = 480 sq ft − 21 − 16 = 443 sq ft
  • Internal plaster (12 mm, 1:6): 4.43 × 0.7 = about 3.1 bags, 4.43 × 5.2 = about 23 cft sand
  • Ceiling (144 sq ft, 6 mm, 1:3): 1.44 × 0.6 = about 0.9 bag, about 3.3 cft sand

Plaster Good Practice

  • Dampen the wall before plastering.
  • Fix mesh across junctions of walls with columns and beams.
  • Apply external plaster in two coats, the first roughened to key the second.
  • Cure for at least 7 days.
  • Avoid plastering in direct afternoon sun in Hyderabad's summer.

The Short Version

Area × thickness × 1.27 × 1.2, split by the mix ratio. Per 100 sq ft, plan about 0.7 bag for 12 mm internal plaster, 1.6 bags for 20 mm external, and 0.6 bag for ceilings.

Frequently Asked Questions

How much cement is needed for 100 sq ft of 12 mm plaster?

About 0.7 bags of cement and about 5 cft of sand for 1:6 plaster, including a 20 percent allowance for uneven surfaces and joints.

How much cement for external plaster?

For 20 mm external plaster in 1:4, about 1.6 bags of cement and 8 cft of sand per 100 sq ft, including allowances.

What thickness should plaster be?

Commonly 12 mm for internal walls in one coat, 15 to 20 mm for external walls in two coats, and about 6 mm for ceilings.

Why add 20 percent to the plaster volume?

Walls are never perfectly flat. Mortar fills joints, hollows and uneven areas, so estimators add an allowance, commonly 20 percent, on top of the dry volume.

What is the dry volume factor for plaster?

About 1.27. The wet mortar on the wall occupies less volume than the dry cement and sand that make it, so the wet volume is multiplied by about 1.27 to get dry materials.

Get the lowest price in Hyderabad

Worked out your quantities? Put them into a free calculator, then see what they cost today.

More Guides

Get the Clyft app

Compare quotes from suppliers and order in minutes.

Download on the App StoreGet it on Google Play
The Clyft app showing supplier quotes for a cement order